Loudoun pauses votes on new data center and substation applications for up to a year
The pause, adopted November 17 and retroactive to September 15, could affect 33 active applications while the county rewrites its data center rules.

Key dates at a glance
Loudoun County is pressing pause on new data center decisions. On November 17, the Board of Supervisors voted to stop acting on legislative data center and electrical substation applications for up to 12 months, the maximum Virginia law allows, the county announced. The pause is retroactive to September 15.
The vote was 7-1-1, according to a release from the office of Algonkian District Supervisor Juli Briskman, who led the effort.
What the pause does
Developers can still submit applications for data centers and substations, and county staff and the Planning Commission can keep reviewing them. But the board does not plan to hold its own public hearings or final votes on those applications until it finishes rewriting the county’s comprehensive plan and zoning rules for the industry. The pause ends when the board adopts those changes.
The county says the pause could affect 33 active legislative applications. Virginia law gives the board 12 months from an application’s Planning Commission hearing to act, and at least nine applications are expected to hit that deadline before the new rules are done. Staff will ask those applicants to agree to wait voluntarily.
The exceptions
- Applications for properties in the Route 28 Tax District are not covered.
- Substations that qualify as grid reliability projects are exempt, though they still go through the board’s review.
- Projects that only need administrative approval, including those grandfathered under 2025 rules, are not affected. The county attorney has said the board lacks authority for a broader moratorium.
Why families should care
Loudoun has about 245 data center buildings built or under construction, totaling around 58 million square feet, with another 55 million square feet approved or in review, according to the release. Residents have raised concerns about noise, air quality, and substations and transmission lines near homes. The next phase of rules will look at how close data centers and substations can be to neighborhoods, schools and other sensitive uses, along with building heights, noise and onsite power generation.
What comes next
That second phase is expected to be completed in July 2027. The first phase, finished in March 2025, generally ended by-right data center development, so new projects must win special exception approval from the board. Residents can follow the work at the county’s data centers page.
Next door in Prince William
In neighboring Prince William County, the PW Digital Gateway data center project next to Manassas National Battlefield Park ended in July after developer QTS withdrew its appeal, following court rulings that the county’s rezonings were void, WTOP reported.