Maryland eyes restart of American Legion Bridge replacement as a public-private deal
A state memo outlines a scaled-back 6.5-mile project, but a financial deal might not close until early 2029 and construction is years away.

Key dates at a glance
The American Legion Bridge, the Capital Beltway crossing between Montgomery and Fairfax counties, is back on Maryland’s to-do list. But anyone hoping for relief from the daily backups will have to wait years.
What Maryland is considering
The Maryland Department of Transportation has drafted a pre-solicitation memo to test private-sector interest in replacing the bridge and adding lanes nearby, Maryland Matters reported in a story republished by The Daily Record. State officials confirmed the memo is authentic but cautioned that no decision has been made to deliver the project as a public-private partnership, known as a P3, or to move ahead with any solicitation.
The new version is smaller than the plan proposed under former Gov. Larry Hogan. According to WJLA, the memo covers about 6.5 miles and would:
- Replace the American Legion Bridge.
- Add two high-occupancy toll lanes in each direction along about four miles of I-495, from the Virginia express lanes to the I-270 west spur.
- Convert existing HOV lanes and add managed lanes along about two miles of the I-270 west spur.
The original plan was estimated at $7.6 billion. A state official told Maryland Matters the new version would still cost billions, though not $7 billion, and that updated cost estimates are needed.
The timeline
According to the draft memo, the state could hold an industry forum and meetings with potential contractors first, possibly by the end of this year, then invite P3 concepts in the first part of 2027. The Board of Public Works could be asked to designate the project a P3 in mid to late 2027, and the state could close on a financial agreement by early 2029. Construction would follow.
The money question
Maryland has applied for $864 million from the federal Bridge Investment Program for eight I-495 bridges, including the American Legion Bridge. State officials told WJLA that federal money could help with costs such as buying right-of-way whether or not the project becomes a P3. A transportation advocate quoted by Maryland Matters argued that the state’s transportation trust fund has no room for big capital projects, which is why officials are looking at private financing.
Why it matters
More than 230,000 vehicles use the bridge each day, WJLA reported. State Highway Administrator Will Pines told Maryland Matters the state recorded 1,000 crashes over three years along the stretch proposed for widening, about a third involving an injury or death, and officials estimate the project could cut those injuries by as much as 28 percent. On the Virginia side, VDOT’s 495 NEXT project extended the 495 Express Lanes about two and a half miles north to the George Washington Memorial Parkway interchanges near the bridge, and a new shared-use trail along that stretch opened June 27. Maryland has no matching project at the river yet.
What to watch
The next signs of progress would be an industry forum and a formal request for concepts in 2027. We will follow the state’s decisions and the federal grant.